For those that are curious.
JT cycle time will be around 2 minutes and 30 seconds.
JL cycle time is around 53 seconds
JK use to run at 1 minute and 10 seconds
Unfortunately no, I didn't put my transfer in to go to the JT side. They closed the transfer process in January. Won't open again until JT is out of launch phase
Update. JT is going to critical launch.
80 Units were built yesterday on 1st shift, all white Rubicons . All were built for the Government. So for all who doubted me, **** it.
I would be more worried about the suppliers not being able to keep up. JL and JT share a lot of the same parts. JL goes down all the time due to lack of parts. It's going to be interesting to see how this works
Production has started and the JTs are going to the dealerships 1st. They decided to hold off on the 7k government order for now. This could change by the time I'm done with this sentence
The JL shutdown to retool for the hybrid engine has been moved up. We will now be shutdown April 18th to May 13th. (subject to change). We are working 7 days a week until then.
The Government order for just over 7k JT's has been verified. These 7k units must be built before any can be sold to...
Sorry for the delay but I didn't want to post anything until I talked to someone that knew what they were talking about. Yes they government has ordered 7,000 JT's, not 60k. That's all I know right now.